Friday, February 22, 2013

W17_LUCKY_Fine Tuning the Decision to put up contractor claim or not to put up contractor claim using Decision Tree


W17_LUCKY_Fine Tuning the Decision to put up contractor claim or not to put up contractor claim using Decision Tree

1.      Problem Recognition

A friend of mine who is a contractor has approached me for advice. He has essentially completed the construction of the block of flats under a fixed price contract. There have been budget costs overrun, unfortunately. Although, not losing money overall, the overrun has substantially reduced his profit.

2.      Problem Definition

My friend believes that the cost overrun was caused by delays attributable to the owner in the form of late deliveries of owner-furnished materials, slow reviews of submittals, etc.

In a previous blog, it has been determined that submitting a claim appears to yield a positive return. But what decisions should be taken in what sequence to assure this positive return?

I would like to solve it using the Decision Tree Tool and Technique once again.

a.      Assumptions

Key assumptions include:

·         The preliminary estimate of delay costs, both direct and indirect, is USD1 million

·         The owner is generally unreceptive to claims for indirect costs on change orders

·         There is no provision for the use of arbitration for dispute resolution

·         The contract does not have damages for delay clause, as none of the delays were for force majeure

·         It will cost $20,000 to prepare the claim

 

3.      Feasible Alternatives

Feasible alternatives include:

1.      Do not submit the claim

2.      Submit the claim and owner request a negotiation

o   This option has 50 per cent probability

o   If it goes well, chances of recovering the amount are as follows

§  $750,000 – 10%

§  $500,000 – 50%

§  $250,000 – 40%

3.      Submit the claim and owner rejects it. Two choices available

o   Leave off

o   Request arbitration (Estimated cost $20,000)

§  30 per cent probability

o   If it goes to arbitration, chances of recovering the amount are as follows

§  $750,000 – 10%

§  $500,000 – 50%

§  $250,000 – 40%

4.      Owner rejects arbitration. Two choices available

o   Leave off

o   Pursue legal action (Estimated cost to file suit: $50,000)

§  70 per cent probability

o   It could result in out-of-court settlement, chances of recovering lower amount are as follows

§  $500,000 – 20%

§  $250,000 – 50%

§  $100,000 – 30%

o   Time to file suit and claim estimated to be 1 year

§  Time-value –of-money at 12 percent per year

5.      Owner not receptive to out-of-court settlement

o   Legal cost increase by $100,000 to bring case to trial

o   It could result in chances of recovering amount are as follows

§  $500,000 – 40%

§  $250,000 – 40%

§             $0 – 20%

o   Time to pursue trail to final judgment estimated to be 5 years

§  Time-value-of-money at 12 percent per year

 

4.      Development of outcomes  for each alternative

There are three decision points:

1.      The decision to submit or not to submit

2.      If claim is rejected, whether to pursue arbitration or not to pursue arbitration

3.      If arbitration is rejected, whether to pursue legal action or not to pursue legal action

There are three intermediate event nodes towards the ultimate outcomes as follows:

X – From which my friend can choose to negotiate or reject claim

Y – From which my friend can either agree to arbitrate or reject arbitration

Z – From which my friend can either go for trial or settle out-of-court

The following calculations results:

Step One

Determining the expected value, Ev

·         Outcome A: Don’t submit option - Ev = $0

·         Outcome B: Claim submitted, negotiation results

Ev = $1,000,000 (0%) +$750,000 (0.1) + $500,000(0.5) + $250,000(0.4) = $425, 000

·         Outcome C: Leave off option - Ev =  $0

·         Outcome D: Seek arbitration , Ev  = $425, 000

·         Outcome E: Arbitration rejected, Ev = $0

·         Outcome F: Possible legal action, at time of award, with 90 per cent probability

Ev = $500,000 (0.2) + $250,000(0.5) + $100,000(0.3) = $255, 000

Calculating the present value of the outcome at Node Z –

PV = $255,000 – (P/F, 12%, 1 yr.) = $228,000

·         Outcome G: Going to court,  with 10 per cent probability

Ev = $500,000 (0.4) + $250,000(0.4) + $0(0.2) = $300, 000

Calculating the present value of the outcome at Node Z –

PV = $300,000 – (P/F, 12%, 5 yr.) = $170,000

4.      Selection Criteria

The selection criterion is to use the most favorable net expected value at the original decision node and tracking it back through the tree to determine the most favorable decision.

5.      Analysis and Comparison of the alternatives

 

Step Two

Working backwards through the paths and using the following formulas:

 

Net outcome = (Expected value) – (Present Value of costs)

Percent Probability = sequential product of individual probabilities of occurrence

 

·         Net Outcome A: Zero; percent probability = zero

·         Net Outcome B: $425,000 - $20,000 = $405,000; percent probability = 50%

·         Net Outcome C: Zero; percent probability = (50%)(0%) = 0%

·         Net Outcome D: $425,000 - $20,000-$40,000  = $365,000; percent probability = (50%)(30%) = 15%

·         Net Outcome E: Zero; percent probability = (50%)(70%)(0%) = 0%

·         Net Outcome F: $228,000 - $20,000-$50,000  = $158,000; percent probability = (50%)(70%)(90%) = 31%

·         Net Outcome G: $170,000 - $20,000-$50,000 -$71,000 = $29,000; percent probability = (50%)(70%)(10%) = 4%

 

6.      Selection of preferred alternative

In this case the resultant advice that I would give my friend will be: (1) pursue the claim; (2) if the claim is rejected, seek arbitration; and (3) if arbitration is rejected, take legal action hoping for out-of-court settlement. The odds for winning the case are very slim (4%) for an outcome of $29,000.

The best option would be to pursue the claim hoping for a negotiated resolution with 50% probability of achieving the expected value of $405,000 otherwise back off with a loss of only $20,000, the cost of preparing the claim

7.      Performance monitoring and post evaluation of results

The precautions against seared relationship with the client, bad reputation in the market place and loss of valuable time are worthy of mention to my friend for serious consideration. Perhaps an improved relationship with the client would eliminate this type of incident in the future.

 

 

 

 

Reference

1.      Sullivan, W., Wicks, E., Koelling, P., Kumar, p., & Kumar, N. (2012).Chapter 12 Probabilistic Risk Analysis (pp. 528 - 533). Engineering economy (15th edition). England: Pearson Education Limited.

2.       Brassard, M. & Ritter D. (2010). Chapter 24 Tree Diagram (pp.200 – 209). The Memory Jogger 2 (2nd edition). USA:GOAL/QPC

3.      Giammalvo, P. (2012, October 22). Integrated portfolio (asset), program (operations) and project management methodology course (cost engineering) slides (An AACE methodology course). Lagos, Nigeria: Lonadek

1 comment:

  1. Also awesome, Lucky!!!

    Another good treatment indicating you know and understand how to use this tool/technique under different or real life circumstances.....

    Just keep doing what you committed to do in the beginning each week and you should be in good shape by the time we meet face to face...

    BR,
    Dr. PDG, Jakarta

    ReplyDelete