Thursday, January 24, 2013

W10_Ocharlie_Resource Loading and Levelling


Problem definition

In scheduling, activity durations depend on availability of resources. Schedule may be logically correct and in agreement with the estimate but can only be achievable when resources are allocated and levelled over the project time.

 Feasible alternatives

Wildly oscillating staffing

Develop the outcome of each alternative

Using the structural skid fabrication of the Retrofit project with man-hour listed below;  

STRUCTURAL SKID FABRICATION 11
Work Package: Skid frame 11A
Work Package No                         Description                                                                               MH      Total MH
11A_001                                               Cut Primary beam members                                           8
11A_002                                               Cut Cross members                                                          48
11A_003                                               Cut Stiffeners                                                                    56
11A_004                                               Fit up beam members                                                      64
11A_005                                               Fit up stiffeners                                                                 36
11A_006                                               Weld beam members                                                      64
11A_007                                               Weld Stiffeners                                                                 30
                                                                                                                                                                               306
Work package: Handrails 11B
11B_001                                               Cut handrail pipe                                                             48
11B_002                                               Fit up pipe                                                                         64
11B_003                                               Weld handrail                                                                  48              
                                                                                                                                                                               160
Work package: Drain Pan 11C
11C_001                                               Cut plate                                                                          6
11C_002                                               Fit up plate                                                                      12
11C_003                                               Weld drain pan                                                               24
                                                                                                                                                                              42
Work package: Grating 11D
11D_001                                               Cut grating                                                                       16                 16
 
Total MH                                                                                                                                                             524  

Table 1 Manhour allocation

Option 1 Resource Loading and levelling

 
Days
1
2
3
4
5
6
7
8
9
10
Structural Skid 11
Fitter
2
2
4
4
4
4
4
4
4
4
Welder
0
0
1
1
1
1
3
3
3
3
 
 
 
 
 
 
 
 
 
 
 
 

Table 2 Resource loading and levelling by author

The planned % progress based on the allotted man-hours will be as in Table 3 below;

 
 Day
 1
2
3
 4
5
 6
 7
8
9
10
Structural Skid
 
 
 
 
 
 
 
 
 
 
Skid frame
 
 
 
 
 
 
 
 
 
 
 
 
11A_001
100
 
 
 
 
 
 
 
 
 
 
11A_002
16
49
82
100
 
 
 
 
 
 
 
11A_003
 
 
 
12.5
37.5
62.5
87.5
100
 
 
 
11A-004
 
 
25
50
75
100
 
 
 
 
 
11A_005
 
 
 
 
 
 
44
88
100
 
 
11A_006
 
 
 
 
 
 
38
76
100
 
 
11A_007
 
 
 
 
 
 
 
 
20
100
Handrail
 
 
 
 
 
 
 
 
 
 
 
 
11B_001
 
 
 
 
 
 
 
 
 
17
 
11B_002
 
 
 
 
 
 
 
 
 
24
Drain pan
 
 
 
 
 
 
 
 
 
 
 
 
11C_001
 
 
 
 
 
 
 
 
 
100

 Table 3 Planned progress

 

Option 2 No resource loading and levelling

Without resource allocation there is no plan

 Selection of criteria

The attribute for the selection criteria is;

·         Resource availability

·         Project visibility

·         Target delivery

·         Efficiency

 

Analysis of alternatives

Option 1 Resource loading and levelling

Resource loading involves allocation of resource requirements on each individual activity. Resources are limited and for the use to be optimized they have to be allocated to tasks and their use tracked to eliminate wastes. Levelling is the efficient utilization of the resources over the project life. From the resource loading of table 2, the number of welders determines the number of welding machines so with fitters and grinding machines. No point allocating welding when there is no welding machine or when fit up is still ongoing. With the man-hour allocation of each task, the progress plan can be generated from which the actual progress can be compared.

Option 2 Blind allocation

Without resource allocation, it is impossible to know if schedule can be met. Not having a resource plan is an assurance of schedule delays and projects being run blindly.

Selection of preferred alternative

Schedule can only work when it is based on available resources. Resource loading includes defining the necessary resources needed to execute each task within the allocated time frame. This allows for a plan for staffing, material and equipment requirement from early start schedule and from late start schedule to be developed. This can then be levelled over the project duration to maximise efficiency. With this resource availability is assured and project visibility is guaranteed.

Performance monitoring and evaluation

With schedule resourced and levelled a plan is generated. This forms the baseline of progress measurement and status reporting.

References

Orczyk, J. J. Project Labour Cost Control, Skills & Knowledge of Cost Engineering (5th ed.), (PP 21.1.-21.6) WV, AACE International

Humphreys, G. C. (2011). Resource Loading And Levelling The Schedule, Project Management Using Earned Value (2nd ed.), (PP. 189-196) CA, Humphreys & Associates Inc.

Humphreys, G. C. (2011). Establishing The Performance Measurement Baseline, Project Management Using Earned Value (2nd ed.), (PP. 519-527) CA, Humphreys & Associates Inc.

 

 

1 comment:

  1. Awesome, Charlie......

    Doing a really great job, but my only question is why did you list only one feasible alternative? Then measure or analyze two of them?

    Nothing wrong with what you ended up doing except for the fact that you should have listed both alternatives?

    Anyway, everything else was just fine.....

    BR,
    Dr. PDG, Jakarta, Indonesia

    ReplyDelete