Problem definition
For project visibility the individual tasks of the
project has to be tracked and progress measured. Without progress tracking,
management of the project is run blindly with resultant schedule and cost over runs.
There are six different methods of measuring progress;
Unit completed- for activities involving quantities
requiring same level of effort
Incremental milestones- for activities with sequential
tasks
Start/Finish- for activities that level of effort cannot
be readily measured
Supervisor opinion- where the level of effort is based on
supervisor`s judgement
Cost ratio- activities which are spread over a long time
and whose cost is budgeted on lump sum.
Weighted or Equivalent units- for activities with overlapping subtasks and
last for long period.
Feasible alternatives
For the progress measurement the weighted or equivalent
units shall be used in this calculation
Develop the outcome of each
alternative
Using the
structural skid fabrication of the Retrofit project with man-hour listed below;
Table 1 Manhour allocation
Table 2 Resource loading and levelling by author
If the
weighting factor for the structural skid fabrication is
Skid frame
70%
Handrail 15%
Drain pan 10
Grating 5%
The percent
contribution of each of the subtasks is shown in table 3
Table 3 Percent
contribution
To calculate
the performance indices if the actual percentage complete on the 8th
day is 40% and actual hour spent is 240hrs
Selection of criteria
The measurement criteria are;
·
Earned value
·
Cost performance Index (CPI)
·
Schedule Performance Index (SPI)
·
Cost Variance
·
Schedule Variance
Analysis of alternatives
Actual hours spent = Actual cost of work performed ACWP =
240hrs
% complete = 40%
Earned Value = Budget Cost of Work Performed BCWP = %
complete x Budget At Completion (BAC)
BCWP= 0.4 x 524 = 209.6
Cost Variance = BCWP – ACWP = 209.6 – 240 = -30.4
Schedule Variance = BCWP – BCWS = 209,6 – 265.52 = -55.92
CPI = BCWP/ACWP = 209.6/240 = 0.87
SPI = BCWP/BCWS = 209.6/265.52 = 0.79
Estimate At Completion EAC = BAC/CPI = 524/0.87 = 602
Selection of preferred alternative
Progress measurement allows status visibility at any
point in time so that management can make decisions to stay the project on
course. Analysis of the data helps in identification of early warning of future
costs and schedule impacts.
Performance monitoring and evaluation
The data from the analysis shows that the project is
running at cost overrun and schedule delay. Urgent action need to be taken by
identifying the schedule drivers and putting in measures to make up for lost time
and eliminate wastes.
References
Orczyk, J. J. Progress Measurement and Earned Value,
Skills & Knowledge of Cost Engineering (5th ed.), (PP 14.1.-14.6)
WV, AACE International
Humphreys, G. C. (2011). Performance Measurement
Calculations And Estimates At Completion, Project Management Using Earned Value
(2nd ed.), (PP. 545-558) CA, Humphreys & Associates Inc.
Humphreys, G. C. (2011). Establishing The Performance
Measurement Baseline, Project Management Using Earned Value (2nd
ed.), (PP. 519-527) CA, Humphreys & Associates Inc.
Doing a really fine job Charlie.......
ReplyDeleteKeep up the good work. No clue what is happening to the rest of your team, but keep on leading by example.
It is obvious to me you are learning a lot, which is what the objective of this course is....
BR,
Dr. PDG, Jakarta