Problem definition
NORSOK Z-014 recognised as Standard Cost Coding System
(SCCS) presents a system for coding cost and weight estimates and data
collection and collating.
NORSOK Z-014 comprises 3 sets of complementary sub-coding
system. Using the Jean-Yves Moine`s 3D WBS theory, are the 3 coding systems
distinct and independent?
Feasible alternatives
Jean-Yves Moine developed a theory which classifies WBS in
3D model;
Areas (GBS, Geographical Breakdown Structure) – Where the
work is done
Products (PBS, Product Breakdown Structure), work components
– What is being done?
Activities (ABS, Activity Breakdown Structure), How is it
being done
This is depicted in fig. 1 below
Jean-Yves explains that there are 3 dimensions that describe
the work seen like one cube in 3D. One time schedule tasks are the little cubes
inside the WBS cube. For instance in the fabrication project, we
construct/install (ABS) skids, piping (PBS) onshore/offshore (GBS).
Jean-Yves surmises thus: WBS = GBS x PBS x ABS
WBS is a crossing between the 3 breakdown structures.
Develop the outcome
of each alternative
NORSOK Z 014 comprises 3 sets of complementary sub-coding
system namely;
Physical Breakdown Structure PBS which defines the
physical/functional components of a project
Standard Activity Breakdown SAB which defines the phases or
timescale during which activities occur
Code of Resources COR classifies the complete scale of
resources involved in the project.
Selection of criteria
In the fabrication project, Jean-Yves opins that fabrication
(ABS) of spools, structures, supports (PBS) is done somewhere (GBS). Consider
fig. 2
The project is executed in 2 zones onshore(GBS) and offshore (GBS) to
generate products (PBS) through various activities (ABS). In Zone 1 onshore piping spools (Product #1.1)
and Structural skid (Product #1.2) are produced through
fitting (Activity #1.2.1) and welding (Activity #1.2.2).
Jean-Yves Moine developed the equation
WBS = GBS x PBS x ABS
Thus for the above instance
Onshore – pipe spools – fitting/welding
Each branch of the WBS is a task and the link is as above.
Analysis of
alternatives
The 3D WBS theory identifies 3 main dimensions that identify
the work: the zones (GBS), the Products (PBS) and the activity (ABS).
NORSOK Z-014 identifies 3 cost coding systems: the Phase or
time scale (SAB), the Physical/Functional components (PBS) and Code of resources (COR).
The Phase is location the products (physical/functional components) are executed with various resources employed in the activities. Thus COR are the various cost
elements expended in the activities (ABS) to generate the products (PBS) during the SAB (GBS)
From WBS = GBS x PBS x ABS
We have WBS = SAB x PBS x COR
Onshore – pipe spools – resource costs
Resources generate spools in a location
Selection of
preferred alternative
The analysis above shows that the 3 NORSOK Z-014 codes are
compatible with the 3D model fig. 3
The 3 dimensions are not distinct and independent as
activity can only happen when there is something to produce and this has to be
performed in a location or time scale.
Resources are employed to produce functional components in a
location or at given project phase.
Thus the 3 NORSOK Z 014 codes are complementary
Performance
monitoring and evaluation
There are interfaces between the 3 codes which run in the
same time as resources are deployed to make components in a project phase.
References
Jean-Yves Moine (2012). 3D WBS model. (online). Available at
http:3D-wbs.blogspot.fr {last Accessed 14/12/2012}
Z-014 Standard Cost Coding Systems (SCCS) (Rev. 2 May 2012)
Retrieved from
www.standard.no/en/sectors/.../NORSOK.../Z.../Z-014
Humphreys, G. C. (2011). Definition of Scope, Work Breakdown
Structure (WBS) and Dictionary, Project Management Using Earned Value (2nd
ed.), (PP. 45-58) CA, Humphreys & Associates Inc.
Hollman, J.K. (Ed}. (2012). , Plan Project Scope and Execution Strategy
development, Total Cost Management Framework. (PP. 147-150) WV, AACE
International
AWWESOME, Charles!!! You have arrived!!!!
ReplyDeleteNow that you are starting to understand the multi-dimensional basis of these WBS models, I highly recommend that you take a REAL case study from your working environment and apply the Norsok coding structure to it.
See if it does or does not work "better" than what you are doing now......
Keep up the good work!!!
Looking forward to seeing more good postings like this coming from you in the remaining weeks.
BR,
Dr. PDG, Jakarta
In the 3D WBS model, there is a fourth dimension, the Organization (OBS/RBS). It is the colors of the 3D little cubes (tasks). May be the COR of NORSOK come on this fourth dimension.
ReplyDeleteBest regards, Jean-Yves Moine