W3_Joseph Adewale_Importnace of Earn
Value to other management practices
1.
Problem recognition, definition, root
cause analysis and evaluation
I.
Problem recognition
In one of the site report
received, the percentage of physical work done by the contractor was misplaced
with actual expenditure. The project was the construction of 3,600m of line
drain at the rate of 600m per week. The project is expected to be completed
within six weeks. Each drainage length is given at the rate of N25, 000.00 per
linear meter.
The Project manager was newly
employed, the site is his first assignment, the report sent did not give basis
for recommending payment to the contractor he is supervising. Hence, the
missing parameter is the earn value of physical work done by the contractor.
II.
Problem definition: Misplacement of the principle of “quantum merut” on the project site
III.
Root cause analysis and evaluation: Root-cause analysis conducted showed that percentage
of physical work completed was missing in the report submitted.
2.
Development of feasible alternatives
Among alternatives available for consideration in are:
I.
Budgeted
cost of work scheduled (BCWS)- this is the overall planned budget on the
project
II.
Actual
Cost of work Performed (ACWP)- this is the actual cost to do the work
III.
Budgeted
Cost of work Performed (BCWP)- this is budgeted cost of what was completed
(Earn value)
3.
Development of outcomes for each
alternative
I.
BCWS:
This is what is planned to be spent on the drainage works.
I.e. 3,600x25, 000.00=90,000,000.00
II.
ACWP:
At week four, only 2,300m length of drainage works was achieved.
III.
BCWP:
This is the earned value of physical work completed
Week
|
1
|
2
|
3
|
4
|
5
|
6
|
Length Done (M)
|
600
|
500
|
800
|
400
|
|
|
BCWS
|
15,000,000.00
|
15,000,000.00
|
15,000,000.00
|
15,000,000.00
|
15,000,000.00
|
15,000,000.00
|
BCWS cum
|
15,000,000.00
|
30,000,000.00
|
45,000,000.00
|
60,000,000.00
|
75,000,000.00
|
90,000,000.00
|
ACWP
|
15,000,000.00
|
12,000,000.00
|
15,000,000.00
|
9,000,000.00
|
|
|
ACWP cum
|
15,000,000.00
|
27,000,000.00
|
42,000,000.00
|
51,000,000.00
|
|
|
BCWP
|
15,000,000.00
|
12,500,000.00
|
20,000,000.00
|
10,000,000.00
|
|
|
BCWP cum
|
15,000,000.00
|
27,500,000.00
|
47,500,000.00
|
57,500,000.00
|
|
|
SV
|
0.00
|
-2,5000,000.00
|
5,000,000.00
|
-5,000,000.00
|
|
|
CV
|
0.00
|
500,000.00
|
5,000,000.00
|
1,000,000.00
|
|
|
% Complete
|
16.67
|
30.56
|
52.78
|
63.89
|
|
|
4.
Selection of criteria
The criteria for selecting the most appropriate value to recommend
payment upon these:
I.
Conformance
to specification requirement
II.
Terms
and condition for contract agreement must be met
III.
Work
must be physically completed as measured.
5.
Analysis and comparison of the
alternatives
The problem statement analyzed two methods:
I.
Traditional
management method: This approach uses two data sources. The Budget cost of work
Scheduled (planned value) or Planned expenditure and Actual cost of work
performed ( Actual Cost) or actual expenditure
II.
Earn
value management: This method uses three data sources. The Budgeted cost of
work Scheduled (BCWS), budgeted cost of work performed (BCWP) and actual cost
of work performed (ACWP)
6.
Selection of preferred alternative
Alternative II is preferred since it satisfied the three criteria for
recommending payments to the contractor. The fourth week report would have
been:
a. % Complete = (BCWPcum/∑BCWS)x100
=
(57,500,000/90,000,000) x100
= 63.89%
b. And not: = (ACWPcum/∑BCWS)x100
=
(51,000,000/90,000,000) x100
= 56.67%
The new project manager’s recommendation for payment to the contractor
was 56.67% completion whereas the contractor has worked up to the level of
63.89% physically on site.
7.
Performance monitoring and post
evaluation of results.
There is need to monitor progress of work done physically on site at the
end of working week to keep tracking progress and check performance. This will
enable the project manager to snap earn value of physical work done by each
contractor and also enable check on errors can could accrued over a long period
of time. Also accurate data will be ready to recommend for contractor payments
at each milestone.
8.
References:
I.
Garry C.
Humphrey, (2011) Project management using earn value (2nd Edition)
(Chapter 1 (pp. 32-42) CA USA Humphrey & Associates inc.
II.
Tate,T, & Stackpole,C. (2006) Controlling
Project Progress. The advanced
project management memory jogger(1st ed) (chapter 7) (pp.91-94). Salem,NH:
GOA
III.
Giammalvo,
P. D. (2010). AACE Certification Prep Course [PowerPoint slides], Day 5. Lagos: Nigeria.
IV.
Sullivan, W.
G., Wicks, E.M., & Koelling, C.P. (2009). Engineering economy and design
process. In M.J. Horton (Ed.), Engineering
economy (14th ed.) (chapter 1.) New Jersey, NJ: Pearson
Education, Inc.
AWESOME Joe!!! I loved it!!! Nice case study and you clearly are applying the tools and techniques we are learning about to a real job. Just cannot expect anything more than this......
ReplyDeleteWhat my challenge to you would be for your W5 posting, take this same case study, but this time, using the same data, calculate the EAC using the two formulae shown on the DAU Gold Card.
What is the CPI? SPI? CV? SV? (All from the DAU Gold Card)
Also calculate the BEI and the Hit/Miss ratio for each week. (Again, from the Gold Card)
If you do your W5 posting TODAY, it will not only put you AHEAD of schedule (SPI >1.0) but it will also help you contribute to fixing the mistakes on the Weekly Report, which is now a full two weeks behind schedule.
The only small mistake is you cited Humphrey's incorrectly. It should be last name first, then first name, middle initial- i,e, Humphrey's Gary C.
Other than that small error you are definitely on the right track. PLEASE take the time to identify one of your colleagues who is struggling with this blog project and help mentor them. Remember, working together as a team makes things easy for EVERYONE and helps ensure success of the projects and the entire program.
BR,
Dr. PDG, Jakarta