Tuesday, November 20, 2012


W4_Joseph Adewale_Identification of negative float, effect and elimination
1.      Problem recognition, definition, root cause analysis and evaluation
                                I.            Problem recognition
Negative float was observed in one of the site schedule chart attached to a report. Although, it skipped verification at the initial phase, but while appraising the project status it was discovered that the project manager wanted to finish the rehabilitation job and process payment before government coffer is closed for the year. The effect is felt on the productivity curve of resources allocated to the project.
Problem definition: Scope definition is a vital phase in project life cycle, so also is the detail scheduling of the project itself. Float is a measure of how much a project can slip without impacting the entire project duration. However, negative slope is not an ideal situation; it affects the health status of the project due to poor resource management.
                              II.            Root cause analysis and evaluation: The major cause is the influence of authority imposition of deadline to project completion and inexperience of the project manager to advice on the effect.
2.      Development of feasible alternatives
Among alternatives available for consideration in are:
                                I.            Let the days slip
                              II.            Add resources to the project
                            III.            De-scoping the process
                            IV.            Improve the work process
3.      Development of outcomes for each alternative
Let’s consider the original finish date as 47 days (Eight weeks) while imposed date as 42 days (seven weeks)
WBS
Activity
Duration
ES
EF
LS
LF
Float
1.1.1
A
5
1
5
-5
0
-5
1.1.2
B
4
6
9
1
4
-5
1.1.3
C
6
10
15
5
10
-5
1.1.4
D
6
16
21
11
16
-5
1.1.5
E
4
22
25
17
20
-5
1.1.6
F
7
26
32
21
27
-5
1.1.7
G
5
33
37
28
32
-5
1.1.8
H
6
38
43
33
38
-5
1.1.9
I
4
44
47
39
42
-5








                                I.            Let the days slip: This first alternative considers effect of additional budget on the project. Hence the project managers do nothing to arrest the situation.
                              II.            Add resources to the project: Although addition of more resources to the project increase the budget of the project but the target date is met.
                            III.            De-scoping the process: This is only practicable at the initial phase of the project. When the project had gone beyond planning phase, it is impracticable to  alter any project scope
                            IV.            Improve the work process: This address the situation by encouraging incentive like bonuses for meeting target.

4.      Selection of criteria
The criteria for selecting best alternative lie in:
                                                        I.            Meet the deadline
                                                      II.            Has little or no effect on the budget of the project
                                                    III.            Project quality not compromised
                                                    IV.            Scope definition is maintained as stated in the contract document
                                                      V.            Productivity maintained
5.      Analysis and comparison of the alternatives
The problem statement analyzed two methods:
                                I.            Let the days slip: Much effect on budget, productivity might tend to be depreciated due to overloading resources; Quality of work done might not meet standard.
                              II.            Add resources to the project: Budget increase, scope maintained but recourses increased, productivity maintained while meeting the deadline.
                            III.            De-scoping the process: Budget is reduced, deadline is met, and project quality is also ensured. Workers productivity is of high standard.
                            IV.            Improve the work process: Budget is increased while productivity is not guaranteed. Hence quality standard might not be maintained.
6.      Selection of preferred alternative
Based on the analysis of the alternatives, the management is interest in what retains quality standard and saves budget.
Therefore, alternative III is preferred.
7.      Performance monitoring and post evaluation of results.
By de-scoping, fewer tasks are performed while there is room for quality check to ensure that specification standards on the project are maintained. Continuous monitoring is important by PMO to evaluate the level of productivity and quality of work done to meet the set target.
8.      References:
                                I.            Giammalvo, P. D. (2010). AACE Certification Prep Course [PowerPoint slides], Day 4 (pp. 79-88). Lagos: Nigeria.
                              II.            Garry C. Humphrey, (2011) Project management using earn value (2nd Edition) (Chapter 1 (pp. 32-42) CA USA Humphrey & Associates inc.
                            III.            Sullivan, W. G., Wicks, E.M., & Koelling, C.P. (2009). Engineering economy and design process. In M.J. Horton (Ed.), Engineering economy (14th ed.) (Chapter 1.)  New Jersey, NJ: Pearson Education, Inc.





1 comment:

  1. Another EXCELLENT case study, Joe!!! Wonderful!!!

    BUT- my only question is why did you descope? Given the problem statement, the solution you selected doesn't make sense to me in fixing any of the problems?

    You are only 5 days behind schedule. Do you really think descoping is a sensible or practical solution? What will the client think? How will that help increase the billings before the end of the year? If you want to maximize billngs before the end of the fiscal year, wouldn't it make more sense to ACCELERATE the work rather than descope it? You trying to BS me? :-(

    For only 5 days, wouldn't it make more sense to see if you either:
    1) Fast Track by scheduling two or more activities in parallel? OR
    2) Crashing, by adding more resources to the critical path activities?

    I am going to accept this W4 posting, with the provision that you REDO the case study, but for your W6 or W7 posting, set the problem up as a time scaled network diagram. Show us the two possible solutions to get rid of the negative float.

    To make it easy to add the graphics, you can do the problem in either Excel, MPS or Primavera, but then download Snag It by Techsmith http://www.techsmith.com/download/snagit/ then take a screen shot of the graphic you want to use, save it in .png or .pdf format, then paste it into your blog posting. Neat, clean and VERY easy to do.

    Now you are in good shape to do your W5 and W6 blog postings using exactly the same case study, which will put you a very comfortable 2 weeks AHEAD of schedule (SPI >1.0) and that should free up a few more hours to work on your paper?

    Looking forward to at least 2-3 more blog postings before Friday.

    BR,
    Dr. PDG, Jakarta

    ReplyDelete